> For the complete documentation index, see [llms.txt](https://help.sequorplatform.io/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://help.sequorplatform.io/documentacao/documentation-en/registrations/registrations-backoffice/calendar-registration.md).

# Calendar Registration

#### Factory Calendar in Sequor MES

The module **Calendar** is responsible for structuring and managing the **work and downtime periods** of the plant.\
Through it, Sequor MES defines **workdays, holidays, scheduled shutdowns, and operating shifts**, ensuring that all production, capacity, and resource availability calculations are aligned with the factory reality.

#### Module Objective

Allow **the planning and control of the plant's productive time**, by configuring:

* Workdays and non-working days;
* Regional and national holidays;
* Shifts and working hours by day of the week;
* Special operating schedules.

> 💡 **Tip:** the correct calendar configuration is essential for OEE reports, production capacity, time entries, and order planning.

## 1. Access to the module

In the Sequor MES main menu, go to:\
**Registrations → Calendar**

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FQxaeHoS6JAiS4vA7ytJI%2F1%20-%20Icone%20Calend%C3%A1rio.png?alt=media&amp;token=85d5d3b0-046e-44de-8f32-c5d5a438e921" alt=""><figcaption><p>Calendar Registration Icon</p></figcaption></figure>

### 1.1. Initial listing screen

The main screen displays all calendars registered in the system, allowing records to be created, edited, or duplicated.

| Field               | Description                                                   |
| ------------------- | ------------------------------------------------------------- |
| **Calendar Code**   | Unique identifier (e.g.: CA-2025).                            |
| **Description**     | Descriptive calendar name (e.g.: Annual Calendar 2025).       |
| **Valid From / To** | Calendar validity period.                                     |
| **Status**          | Indicates whether the calendar is **Active** or **Inactive**. |

> 💡 **Tip:** keep only **one active calendar per plant and period** to avoid overlapping rules.

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FylEWNeGqGohp3IuzrYVE%2F2%20-%20tela%20criteria.png?alt=media&amp;token=a8429e9b-8de0-462d-a976-b684179748f3" alt=""><figcaption><p>Criteria Screen - Calendar Registration</p></figcaption></figure>

## 2. Calendar Registration Tabs

When creating or editing a calendar, the system displays five main tabs that bring together all plant operating configurations.

### 2.1. Tab **General**

In this tab, the **basic data and validity period** of the calendar are defined.

| Field                     | Description                                 |
| ------------------------- | ------------------------------------------- |
| **Calendar Code**         | Calendar identification (e.g.: CA-2025).    |
| **Description**           | Calendar name (e.g.: Annual Calendar 2025). |
| **Valid From / Valid To** | Start and end dates of validity.            |
| **Active**                | Defines whether the calendar is in use.     |

> **Example:**\
> Code: CA-2025\
> Validity: 01/01/2025 to 12/31/2025\
> Status: Active

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FU4f0cWwUJOu9J9v8mcGc%2F3%20-%20aba%20Geral.png?alt=media&amp;token=f4c40ec7-f2a2-4182-982e-1c346ddd471c" alt=""><figcaption><p>General Tab - Calendar Registration</p></figcaption></figure>

> 💡 **Tip:** use the **duplicate** feature to generate next year's calendar, keeping the rules and adjusting only dates and holidays.

### 2.2. Tab **Non-Working Day**

In this tab, the **non-productive days** that are not classified as national holidays — such as **scheduled shutdowns** or **regional holidays**.

| Field                    | Description                                                    |
| ------------------------ | -------------------------------------------------------------- |
| **Non-Working Day Type** | Event classification (Regional Holiday, Plant Shutdown, etc.). |
| **Description**          | Event name (e.g.: Scheduled Shutdown, RS State Day).           |
| **Date**                 | Date of the non-working day.                                   |
| **Active**               | Defines whether the event is in effect.                        |

> 💡 **Example:**
>
> * Type: Plant Shutdown
> * Description: Scheduled Shutdown
> * Date: 11/09/2025

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FLQisdBQ07siHL4kYX8LY%2F4%20-%20aba%20Dia%20N%C3%A3o%20Trabalhado.png?alt=media&amp;token=e9b47952-daaa-478a-a355-7c97c634fc01" alt=""><figcaption><p>Non-Working Day Tab - Calendar Registration</p></figcaption></figure>

> ⚠️ **Attention:** if there is overlap between a holiday and a plant shutdown, the day will automatically be considered **non-working**.

### 2.3. Tab **Holiday**

Allows registration of **national and local holidays** that impact plant operations.

| Field           | Description                                         |
| --------------- | --------------------------------------------------- |
| **Description** | Holiday name (e.g.: Christmas, Labor Day).          |
| **Date**        | Holiday date.                                       |
| **Active**      | Defines whether the holiday is valid in the period. |

> 💡 **Tip:** keep all registered holidays — including movable ones — to avoid incorrect capacity and work-hour reporting.

> **Example:**
>
> * Universal Fraternity Day – 01/01/2025
> * Labor Day – 01/05/2025
> * All Souls' Day – 11/02/2025
> * Christmas – 12/25/2025

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FSiSKWA4jSqKPJQogdd1D%2F5%20-%20aba%20Feriado.png?alt=media&amp;token=2b1d1610-21f8-4ec9-be41-93a5767387b1" alt=""><figcaption><p>Holiday Tab - Calendar Registration</p></figcaption></figure>

### 2.4. Tab **Work Hours**

In this tab, the **standard work shifts**, by day of the week, throughout the validity period.

| Field                | Description                                     |
| -------------------- | ----------------------------------------------- |
| **Day of the Week**  | Selection from Monday to Sunday.                |
| **Shift**            | Shift code and name (e.g.: T01A – Shift 01 A).  |
| **Start / End Time** | Start and end times of each shift.              |
| **Day Transition**   | Marking for shifts that go past midnight.       |
| **Active**           | Defines whether the shift is active on the day. |

> **Example of 3x8 structure:**
>
> * Shift 01A: 06:00 – 14:00
> * Shift 02A: 14:00 – 22:00
> * Shift 03B: 22:00 – 06:00 *(Day transition: Active)*

> ⚠️ **Attention:** mark **Day Transition** whenever the shift crosses midnight, ensuring correct time and availability calculations.

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FfR6371lpZULg4brXSHuZ%2F6%20-%20aba%20Hor%C3%A1rio%20de%20Trabalho.png?alt=media&amp;token=cb3713d2-faf2-47c6-9774-31ec618f320c" alt=""><figcaption><p>Work Hours Tab - Calendar Registration</p></figcaption></figure>

### 2.5. Tab **Work Schedule for Special Day**

This tab allows configuring **work schedule exceptions** for specific days, without changing the standard shifts from the previous tab.\
It is used in situations such as **reduced shifts, collective overtime, or special dates**.

| Field                             | Description                                             |
| --------------------------------- | ------------------------------------------------------- |
| **Description**                   | Name of the special schedule (e.g.: Special Shift 01).  |
| **Date**                          | Date of application of the schedule.                    |
| **Shift / Start Time / End Time** | Definition of specific shifts and times.                |
| **Day Transition**                | Indicates whether the shift crosses midnight.           |
| **Active**                        | Enables execution of the schedule on the specified day. |

> **Example:**
>
> * Description: Special Shift 01
> * Date: 08/28/2025
> * Shifts:
>   * T01A – 06:30 to 14:30
>   * T02A – 14:30 to 22:30
>   * T03B – 22:30 to 06:30 (Day transition: Active)

<figure><img src="https://2582153898-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FwAMVKtJedtiJ4RrzXGfp%2Fuploads%2FGz6doaTbYdCkMbB77G5i%2F7%20-%20aba%20Escala%20de%20Trabalho%20Para%20Dia%20Especial.png?alt=media&amp;token=432d77f0-6b40-4f98-80c7-725c357dc8a8" alt=""><figcaption><p>Work Schedule for Special Day Tab - Calendar Registration</p></figcaption></figure>

> **Application:** this configuration replaces the normal schedule **only on the indicated date**, without changing the rest of the weekly schedule.

## 3. Best practices

* Keep one **calendar per plant** or operational unit.
* Use **standardized names** (e.g.: CA-2025, CA-2026).
* Register all **fixed and movable holidays** of the year.
* Review **shifts and day transitions** before activation.
* Record **scheduled shutdowns and special days** with clear descriptions.
* Always **verify the validity period** and keep only **one active calendar per plant**.